Pre-commissioning and Commissioning activities of 27km carbon steel Node 4 Transport Pipeline and Node 4 Gathering System, comprising of 33 well head connections.
Project Summary
Preparation of Commissioning procedures;
Commissioning risk assessment activities;
Preparation and approval of AS2885 Operational Documents;
On-site pre-commissioning activities;
Nitrogen leak test of Node 4 Transport Pipeline;
Introduction of gas into Node 4 Transport Pipeline;
Nitrogen purging and introduction of gas into Node 4 Gathering System;
Preparation and delivery of operations training package and handover;
Project delivered ahead of schedule and below budget estimate.