Cape Lambert EPC

Scope
Verbrec delivered the EPC of the 1.9km 10″ pipeline and delivery station at Cape Lambert, in JV with Monadelphous and KT-Pipelines. The pipeline connected to the existing purged, cut and capped Rio Pipeline (PL8).
Project Summary

Mono’s-KT pipelines were responsible for the stations construction for this project. Verbrec was responsible for engineering, procurement, regulatory, technical site support/inspection for the station and commissioning. Verbrec was also appointed operator for PL8 (and the new pipeline) during the commissioning of the interconnected pipeline system.

Verbrec’s Role

  • Engineering
  • Procurement
  • Technical Site Support
  • Commissioning

Location

Cape Lambert, WA

Date

2016