SCOPE

LogiCamms was engaged by FGL to provide:

  • Design and Engineering- from concept to completion
  • Procurement Management
  • Construction Support
  • Pre-Commissioning and Commissioning Procedures
  • Pre-Commissioning and Commissioning Support
  • Project Close-Out support
DESCRIPTION

The Ahuroa Gas Storage Facility stores gas for use by the Stratford Power Station. First Gas upgraded the facility to increase the gas injection and withdrawal rates from 35 to 65 TJ/day.

Scope of the project included providing three additional compressors and a gas conditioning treatment plant.

LogiCamms was engaged by First Gas to provide design, engineering, procurement and construction support services for the expansion at Ahuroa through to plant hand-over documentation and commissioning support. LogiCamms have been part of the FGL led integrated collaborative team from initial project inception to completion.