Scope

Design of 11kV supply to UG mine. This included the design of an 11kV Kiosk at the workshop, HV cable routing, and connection to the 11kV overhead line.

Project Summary

Detail electrical design included the following:

  • Pole Design – Connection to 11kV overhead line at the power pole
  • HV cable routing included the following sections:
  • Underground installation
  • Cable ladder installation
  • HV Earthing and Lightning System design for the kiosk substation.
  • Arc Flash calculations

Related Projects

Beach Energy

Hot Oil Efficiency Study

First Gas

Broadlands Biogas Upgrade

Northstar Energy

Energy Evolution Hub (EEH) Pre-Feasibility Study

Jpower

Latrobe Valley Hydrogen Energy Supply Chain Pilot Plant

Hydrogen Refuelling Station – Red Bus Trial

Petawatt Hydrogen Pilot

5MW Solar Connection Power Study

Arrow Energy

Girrahween to Bellevue Pipeline FEED

Arrow Energy

Lynwood to Jordan Pipeline FEED

Epic Energy South Australia Pty Ltd

Snapper Point EPC Project

Monadelphous for the Armidale Regional Council

Malpas Pipeline Design

Santos

CS1 Jemena Tie-in