The APLNG Wellhead Electrification Project involved detailed design of a large scale HV distribution network from conception to implementation.
Project Summary
The objective of this project was to deliver power to over 2000 CSG Wellheads in Phase 1 & Sustain Phase. To do so involved over 200, 22/3.3kV Substation Kiosks, over 2000km of underground HV cable, over 5000 underground HV cable joints. Verbrec designed fully automated switching using the latest IEC61850 protocol as well as a high-speed differential and logic blocking protection scheme.