- Reviewed the Inline Inspection reports, developed dig-up campaign to validate ILI and completed 6 dig ups.
- Performed Fitness For Service and defect assessment following ASME B31.G and API 579 and provided repair options.
- Implemented pipeline repair on site at several locations to reinstate the pipeline pressure back to MAOP of 10.2MPag.
- Provided Integrity assessment report development a short term and long term strategy to maintain pipeline MAOP.